Recent Projects
These photographs were taken at St John's House in Dudley.
They were taken between october 2003 and December 2003.
The project undertaken was to supply and fit approximately
3,500m²
of 600x600 suspended ceiling tiles and grid over different
floors within the building.
Photograph
1
This photograph was taken on the second floor.
It shows
the grid has been prepared ready for the tiles to be installed.

Photograph
2
This photograph was also taken on the second floor.
The
grid has been installed ready for the tiles to be installed.

Photograph
3
This photograph was taken on the third floor.
This
shows the third floor ceiling near completion. The grid
is up and 90% of the tiles have been installed. Some tiles
had to be kept out to allow access for electrical contractors.

Photograph
4
This photograph was taken on the fourth floor.
This
also shows the floor near completion and that tiles have
been left out to allow access for the electrical contractors.

Photograph
5
This photograph was taken on the fourth floor.
This
shows how the suspended ceilings had to be angled due to
the angle of the building. It also shows how the ceiling
had to be sloped to allow it to join at the top of the window.

Top
|